When our clients in-house commercial lead departed, we were approached to supply a Commercial Manager to provide interim leadership for a major regional highway’s maintenance and renewals programme. The primary challenge was to deliver a £37M annual works programme within a reduced, fixed budget of £27.4M, with future budget increases capped at just 2% annually until 2025.
Recognising that no single initiative could achieve the required savings our team conducted a comprehensive commercial review and applied a data-led strategy to identify multiple efficiency opportunities across the contract which enabled budgetary constraints to be met without compromising service delivery or public safety.
Combined these initial measures saved circa £7.85M with subsequent highlighted secondary efficiencies successfully bringing the original £37M Programme within £27.4M Budget without jeopardising service standards or public safety.
Forward Outlook
With additional new roads being incorporated into the network area next year, and no funding increase, continued commercial rigor and innovation will be essential to maintain. required standards within budget restrictions.
Conclusion
This case study demonstrates how Adeo’s commercial leadership and strategic analysis deliver tangible value by turning financial pressures into improved opportunities, empowering clients to achieve best-value—without compromising on quality or safety.